Algeria's future rail network: Tamanrasset, the mines and the High Plateaus

Published on

Map of the rail network of northern Algeria in 2023, from OpenStreetMap: lines in service in black, lines under construction in dotted blue
Image: Poudou99, via Wikimedia Commons (resized), licence CC BY 4.0

Algeria's rail network has about 5,800 km of lines today, mostly in the North. The State wants to extend it southwards, link it to the mines and modernise what exists: 2,340 billion dinars go to rail in 2026. Here are the major projects, what already runs and what is still to come.

The major projects in figures

Length of the major rail projects (km)
Length (km)
Modernisation of the North-West1,822
High Plateaus line1,046
Laghouat – El Meniaa495
Tébessa – Annaba420
Algérie360, African Development Bank, 2026

Southwards: Algiers – Tamanrasset

The longest project is a line of more than 2,000 km between Algiers and Tamanrasset. According to MEED, it is designed for 220 km/h for passengers and 100 km/h for freight. On 4 October 2026, the President of the Republic ordered the immediate launch of the Laghouat – El Meniaa – In Salah – Tamanrasset sections, with the whole line expected to be handed over at the end of 2028.

Between Laghouat and El Meniaa the line is 495 km long. Its second phase, the 230 km from Ghardaïa to El Meniaa, is financed with 878 million dollars from the African Development Bank.

Further north, the train already links Djelfa to Laghouat via Boughezoul: see the Djelfa – Laghouat line page (in French).

Rail for the mines

The High Plateaus and the North-West

The High Plateaus line, 1,046 km long, is due to be completed in 2026 with its last 73 kilometres, between Tiaret and Tissemsilt. Part of it already runs: a daily train leaves Bordj Bou Arréridj for Tissemsilt at 4:30 pm, see the Bordj Bou Arréridj – Tissemsilt line page. In the North-West, 1,822 km of existing track are to be modernised.

What it changes for travellers

The mining lines serve freight first; Algiers – Tamanrasset is planned for passengers too. A line is only useful to travellers once its timetable is published: our line pages show only the trains actually scheduled by SNTF.

The timetables of the SNTF lines in service are also in the free Rekba app, if you would rather have them at hand.

Sources

  1. Algérie360 — 2 340 milliards de DA pour le rail : les 5 projets ferroviaires majeurs de 2026
  2. Banque africaine de développement — 878 millions de dollars pour la deuxième phase de la ligne Laghouat – Ghardaïa – El Meniaa
  3. APS — Le président de la République ordonne le lancement immédiat des tronçons Laghouat – El Meniaa – In Salah – Tamanrasset
  4. MEED — Algeria prepares Algiers – Tamanrasset rail construction
  5. Radio Algérie — La ligne ferroviaire Alger – Tamanrasset
  6. SNTF — site officiel, horaires et billets